M

Mr. Dubey • 52.61K Points
Coach

Q. Risk assessment is

(A) Here each identified risk is analyzed and prioritized
(B) It begins after all hazards are identified. For each hazard, the outcome of the risk assessment process is a statement of acceptability.
(C) The anticipate risks which night affect the project schedule or the quality of the software being developed and to take action to avoid these risks.
(D) None of these
Share

No solution found for this question.
Add Solution and get +2 points.

You must be Logged in to update hint/solution

Discusssion

Login to discuss.

Be the first to start discuss.


Question analytics