Q. Which of the following statement regarding PERT is incorrect?

(A) It establishes the sequence and the relationship between significant programmes events
(B) It is statistical technique which makes decisions
(C) It points out slippages before the fact happens and its impact on others
(D) It helps to formulate new schedules when the existing schedule cannot be met.
Correct : Option (B)