Q. is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.

  • (A) cube rate estimate
  • (B) supplementary estimate
  • (C) maintenance estimate
  • (D) plinth area estimate