M

Mr. Dubey • 52.30K Points
Coach

Q.                      is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.

(A) cube rate estimate
(B) supplementary estimate
(C) maintenance estimate
(D) plinth area estimate
Correct : Option (D)

Share

Discusssion

Login to discuss.

Be the first to start discuss.