Q. During the construction period, price variation clause in contracts caters to

(A) Increase in rates of only importantmaterials
(B) Variation in cost in materials element, labour element and petrol-oil-lubricantelement
(C) Variation in total cost of the project on an ad hocbasis
(D) Rate of inflation
Correct : Option (B)