Q. The direct cost of a project with respect to normal time is

(A) minimum
(B) Maximum
(C) Zero
(D) Infinite
  • Correct Answer - Option(A)
  • Views: 501
  • Filed under category Construction Management
Share

No solution found for this question.
Add Solution and get +2 points.

You must be Logged in to update hint/solution

Discusssion

Login to discuss.

Be the first to start discuss.

Related MCQs

Q. The coefficient of friction between the concrete and soil is

Q. The increase in traffic constitutes the

Q. The fineness modulus of an aggregate is roughly proportional to ?

Q. A bar chart is drawn for

Q. Retarder admixture is used for…..

Q. Originally, Rankine’s theory of lateral earth pressure can be applied to only

Q. The compressive strength of felspar is .......... quartz ?

Q. A Kaplan turbine claims which of the following advantages over a Francis turbine?

Q. A moist aggregate is one ?

Q. In the virtual work method, the virtual quantity is


Question analytics

Share

Embed

WhatsApp

Facebook

Telegram

Share in MCQ Buddy Groups

Share
Embed
Important Links
  • Browse All Categories
  • Subjects
  • Exams
  • Mock Test
  • Advance Search
  • Quiz
  • Duo Test
  • English Topics
Explore More Portals
  • Hindi
  • State wise Portals
  • MCQ Buddy Lab
  • Engineering
  • Programming Portal
  • MB Shorts
  • NCERT Portal
  • Faculties Portal
  • Groups
  • Q & A
  • Spaces
  • Satya Sanatan
  • Keycrypt
Who we are?

We are nothing if we are alone. But we have a huge community of students who are helping you getting good study stuff free.

More Links
  • Download App
  • Advertise with us
  • Contact us
  • Youtube
  • Terms & Conditions
  • Refund Policy
  • Privacy Policy

Since 2020 - 2025 | Proudly Made with ♥ in India

Hosted on Hostinger