Q. The direct cost of a project with respect to normal time is

(A) minimum
(B) Maximum
(C) Zero
(D) Infinite
  • Correct Answer - Option(A)
  • Views: 506
  • Filed under category Construction Management
Share

No solution found for this question.
Add Solution and get +2 points.

You must be Logged in to update hint/solution

Discusssion

Login to discuss.

Be the first to start discuss.

Related MCQs

Q. Construction team means

Q. The piles that are used for protecting structures from ships and floating object is

Q. Which of the following statement is wrong ?

Q. The flow is said to be turbulent when Reynolds number is

Q. The workability of concrete is defined as the

Q. A fine grained soil ?

Q. For Madras catchments, the flood discharge is estimated from Q = C * A (2/3) This forma known as ?

Q. Which factor affects the selection of the floorings?

Q. CPM is

Q. Which of the following pump is preferred for flood control and irrigation applications?


Question analytics

Share

Embed

WhatsApp

Facebook

Telegram

Share in MCQ Buddy Groups

Share
Embed
Important Links
  • Browse All Categories
  • Subjects
  • Exams
  • Mock Test
  • Advance Search
  • Quiz
  • Duo Test
  • English Topics
Explore More Portals
  • Hindi
  • State wise Portals
  • MCQ Buddy Lab
  • Engineering
  • Programming Portal
  • MB Shorts
  • NCERT Portal
  • Faculties Portal
  • Groups
  • Q & A
  • Spaces
  • Satya Sanatan
  • Keycrypt
Who we are?

We are nothing if we are alone. But we have a huge community of students who are helping you getting good study stuff free.

More Links
  • Download App
  • Advertise with us
  • Contact us
  • Youtube
  • Terms & Conditions
  • Refund Policy
  • Privacy Policy

Since 2020 - 2025 | Proudly Made with ♥ in India

Hosted on Hostinger