Q. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

(A) 50 %
(B) Less than 50 %
(C) More than 50 %
(D) 100 %
Correct : Option (C)