Q. Critical Path Net Work helps an engineer

(A) To concentrate his attention on critical activities
(B) To divert the resources from non-critical advanced activities to critical activities
(C) To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
(D) All the above
Correct : Option (D)