Q. During the month of December actual direct labour cost amounted to $39,550, the standard direct labour rate was $10 per hour and the direct labour rate variance amounted to $450 favourable. The actual direct labour hours worked were:

(A) 3,955 hours
(B) 4,000 hours
(C) 3,910 hours
(D) 4,500 hours

Correct Answer - Option(B)