S

Shiva Ram • 30.44K Points
Instructor I

Q. A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of:

(A) Management attention to scope management.
(B) Management planning.
(C) A project expediter position.
(D) A change control system.