J Jitendra Singh • 7.50K Points Tutor III Math Bookmark Embed Report View In MB-Short Q. A can do a work in 6 days and B in 9 days. How many days will both take together to complete the work? (A) 3 days (B) 3.6 days (C) 7.5 days (D) 5.4 days Correct Answer - Option(B) Views: 871 Filed under category Math Share