  • (A) 12
  • (B) 16
  • (C) 10
  • (D) 9
Correct Answer - Option(B)

Explanation by: Indresh Gehalot
A person completes 5/8 part of the project in 10 days.
A person completes the project in 10/5/8 days.
A person completes the project in 10 x 8 /5 days.
A person completes the project in 2 x 8 days.
A person completes the project in 16 days.