Q. A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now so that the work may finish in time ?
  • A. 48
  • B. 56
  • C. 40
  • D. 50

Correct Answer: B