M

Mr. Dubey • 52.30K Points
Coach

Q. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

(A) Total float
(B) Free float
(C) Interfering float
(D) Independent float
Correct : Option (D)