Advance Construction and Equipments MCQs | Page - 4

Dear candidates you will find MCQ questions of Advance Construction and Equipments here. Learn these questions and prepare yourself for coming examinations and interviews. You can check the right answer of any question by clicking on any option or by clicking view answer button.

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 31) the ______ was used as a material for the construction of caisson in the early stages of development of caisson.

(A) Steel
(B) Timber
(C) Cast iron
(D) RCC
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 32) a _____ caisson is open at top and closed at bottom.

(A) Wells
(B) Pneumatic caissons
(C) Cylinders
(D) Box caissons
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 33) a ______ is a caisson which is open at top as well as at bottom.

(A) Well
(B) Box caisson
(C) Pneumatic caissons
(D) Cofferdam
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 34) a _____ are open at bottom and closed at top.

(A) Cylinders
(B) Wells
(C) Box caissons
(D) Pneumatic caissons
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 35) which the given method is used for dewatering of the foundation trenches.

(A) Deep boring
(B) Geophysical method
(C) Well point system
(D) Analytical method
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 36) in case of releasing artesian pressure, which precaution should be taken when the system of well points is adopted.

(A) Pumping rate
(B) Air locks
(C) Duplication of pumps
(D) Blowing action
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 37) the organic chemicals include epoxy resin, polyester resin and other resins are used in which method of dewatering of the foundation trenches.

(A) Well point system
(B) Cement grouting
(C) Chemical grouting
(D) Electro osmosis process
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 38) from given below, which method for the dewatering of foundation trenches is portable and can be easily moved when required.

(A) Pumping
(B) Well point system
(C) Freezing process
(D) Electro osmosis process
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 39) in which method a refrigeration plan of required capacity is need to be installed near the site of work.

(A) Pumping
(B) Well point system
(C) Freezing process
(D) Electro osmosis process
View Answer Discuss Share

Y

Yatendra Sir • 5.66K Points
Tutor III

Q. 40) ______ process consists of making a number of holes in the ground and then filling these holes by the cement grout under pressure

(A) Chemical grouting
(B) Cement grouting
(C) Freezing process
(D) Electro osmosis process
View Answer Discuss Share