Q 1. Hardware study is carried out

(A) after the final system is specified
(B) at the requirements specification stage
(C) before the requirements are specified
(D) whenever management decides it is necessary

V

Vikash Gupta • 33.56K Points
Instructor I

Q 2. Hardware study is required

(A) to find out cost of computer system needed
(B) to determine the type of computer system and software tools needed to meet the final system specification
(C) to make sure that the system does not become obsolete
(D) to find how to implement the system

A

Admin • 36.93K Points
Coach

Q 3. System approval criteria are specified

(A) when the final specifications are drawn up
(B) during feasibility study
(C) during the requirements specifications stage
(D) during system study stage

V

Vinay • 28.75K Points
Instructor II

Q 4. The final specifications are arrived at

(A) after feasibility study
(B) during feasibility study
(C) just before implementation phase
(D) when the system is being designed

S

Shiva Ram • 30.44K Points
Instructor I

Q 5. The main goal of arriving at a final specification is

(A) to tell the organization’s managers how the system will function
(B) to tell the organization’s managers what the proposed system will achieve in a language understood by them
(C) to compute the cost of implementing the system
(D) to assist in designing the system

V

Vikash Gupta • 33.56K Points
Instructor I

Q 6. Initial requirements specification is

(A) not changed till the end of the project
(B) continuously changed during project implementation
(C) only a rough indication of the requirement
(D) changed and finalized after feasibility study

V

Vikash Gupta • 33.56K Points
Instructor I

Q 7. Feasibility study is carried out by

(A) managers of the organization
(B) system analyst in consultation with managers of the organization
(C) users of the proposed system
(D) systems designers in consultation with the prospective users of the system

V

Vinay • 28.75K Points
Instructor II

Q 8. It is necessary to carry out a feasibility study as

(A) top management cannot ensure that a project is feasible before calling a system analyst
(B) top management is not sure what they want from the system
(C) even though top management is in favour of the system, technology may not be mature for implementation
(D) all organizations do it

A

Admin • 36.93K Points
Coach

Q 9. A feasibility study is carried out

(A) after final requirements specifications are drawn up
(B) during the period when requirements specifications are drawn up
(C) before the final requirements specifications are drawn up
(D) at any time

R

Rakesh Kumar • 28.44K Points
Instructor II

Q 10. It is necessary to consult the following while drawing up requirement specification

(A) only top managers
(B) only top and middle management
(C) only top, middle and operational managers
(D) top, middle and operational managers and also all who will use the system